In Botanic Cheltenham, Project Construction Updates

Project Update – June 2020

The preceding eight weeks onsite has been productive with Buildkomm confirming the building completion remains on track for a mid November completion/final inspection and mid December settlement pending the subdivision and new titles are not delayed due to COVID-19.

The following works have been undertaken since our last update:
– Roofing works completed
– Double glazed commercial framed aluminium windows installed
– External wall cladding and eves installed
– First floor render works completed
– Plumbing, electrical and HVAC roughed in
– Thermal, sound and fire rated Insulation installed
– Plasterboard installation has begun – Townhouse 1 completed.