Project Update: March 2020

It’s full steam ahead at 22 Courtney with a total of 8 more major concrete pours before the building tops out by end of March.

As the building begins to take shape, floor fit-outs have begun.

See the site from the crane driver’s nest…

Our September completion schedule is unchanged, although the future is somewhat guided by factors outside of our control. Stay well, stay safe.