Locale, Ivanhoe

Dear Locale Purchasers,

The Developer’s of Locale have passed on the following updates:

  • Crane base, lift core and raft slab all poured.
  • Tower crane installed and commissioned.
  • Shotcrete completed for 90% of site.
  • Bulk excavation completed for 95% of site.
  • Installation of sacrificial struts along Western Elevation in line with IFC basement retention design.
  • Commence structural pad footings throughout SOG.
  • Commence civil drainage.

Key Activities for next reporting period:

  • Bulk excavation works complete.
  • SCW works complete.
  • Civil drainage complete
  • Slab on ground complete
  • Installation of basement precast complete
  • Suspended structure commenced.
  • Water tap in complete

Kind Regards,
Customer Care | Eton Property Group
customercare@etonproperty.com.au