Locale, Ivanhoe
Dear Locale Purchasers,
The Developer’s of Locale have passed on the following updates:
- Crane base, lift core and raft slab all poured.
- Tower crane installed and commissioned.
- Shotcrete completed for 90% of site.
- Bulk excavation completed for 95% of site.
- Installation of sacrificial struts along Western Elevation in line with IFC basement retention design.
- Commence structural pad footings throughout SOG.
- Commence civil drainage.
Key Activities for next reporting period:
- Bulk excavation works complete.
- SCW works complete.
- Civil drainage complete
- Slab on ground complete
- Installation of basement precast complete
- Suspended structure commenced.
- Water tap in complete
Kind Regards,
Customer Care | Eton Property Group