Dear Neue Highett Purchasers,
The developers of Neue Highett are pleased to announce the following works are now underway or completed:
- Basement 2 slabs poured
- Pre-cast columns installed
- In-situ concrete walls next
- Pre-cast to lifts/stairs following
- Basement 1 slabs to be poured approximately end of August
Anticipated completion is expected Q3 2022.