Project Update – July 2022
Dear Neue Highett Purchasers,
The developers of Neue Highett are pleased to announce that the following works have now been completed:
- Basements services well under way;
- Ground floor & Level 1 wall set-outs well under way;
- Level 3 walls onsite awaiting installation in next 2-3 days to start;
- Most of the structure is completed.
Anticipated completion is expected Q1 2023.
Kind Regards,
Customer Care | Eton Property Group