Project Update – September 2021

Dear Park Ave Purchasers,

Milbex are pleased to advise that the following works have been completed onsite:

  • The structure is complete
  • Façade installed on all levels except 18 & 19
  • Wall framing complete up to level 15. Wall lining complete up to level 13.
  • Ceiling lining installed on level 12.
  • Painting commenced up to level 8.
  • Joinery installation commented on level 7.
  • Stone installation commented on level 4.
  • Appliances installed up to level 2.

Anticipated completion is estimated to be December 2021.