Project Update – December 2020

Dear Victoriana Purchasers

JD Group are pleased to advise that construction is progressing well with the following works now complete:

  • Timber flooring and prime painting up to Level 15
  • Joinery installation up to Level 14
  • Tiling up to Level 13
  • Defecting Levels 1-7
  • Energisation Ground Floor – Level 9
  • Commissioning Ground Floor – Level 6
  • Corridor carpet and metal ceiling to Levels 1-9; and
  • Timber battens to Levels 1-5.

Anticipated completion is expected mid-2021.

The team at Eton Property Group wish you and your families a very Merry Christmas and we look forward to bringing you further updates as construction progresses in the New Year.