The development team behind Ivory Ivanhoe are pleased to advise that the following works have been completed onsite:

  • Structural concrete works to the top level of the apartment complex are complete;
  • Metal frame installation on the top level apartment is underway; and
  • Installation of services and mechanical have commenced.

Anticipated completion is expected in mid-September 2021.