Dear Baia Purchasers,
The development team are pleased to announce that construction is progressing very well at Baia Chelsea, the update as of Q2, 2023 is as followed:
Units 1 – 4
Completed
- Framing commenced
Upcoming
- Roofing install
- Cladding install
- Rough in for electrician, plumb, h &C – Fire services rough in work.
- Plaster
Units 5 – 8
Completed
- Internal painting completed
- Cabinetry installed
- Stairs installed
- Waterproofing and screed completed
- Stone templates pick up by stonemason
- External render works and cladding completed
Upcoming
- Stone Installation within 2 weeks
- Tiling works currently occurring
- Flooring installation in 4-5 weeks’ time
- Final paint touch ups to follow
- Fit off for electrician, plumber and heating and cooling
Kind Regards,