The development team are pleased to announce that construction is progressing very well at Baia Chelsea, the update as of Q4, 2022 is as followed:

  • Steel columns have been installed to front 4 units with structural steel beams to be installed next week.
  • Commencement of rough in trades starting in basement will commence within the coming weeks.
  • Necessary waterproofing works around permitter of slab and edge of basement underway.
  • Hebel party walls have been installed to separate each unit as per fire rating requirements.
  • Scaffold scheduled within next 2 weeks to allow roofing to commence.
  • Steel for rear 4 units installed and timber framing has commenced.
  • Bricklayers onsite completing structural brickwork as required.
  • Driveway under screed to be poured this week.
  • Termite protection has been installed.