In Botanic Cheltenham, Project Construction Updates

Project Update – August 2020

Invogue Property are pleased to advise that in light of the recent stage three and four COVID-19 restrictions their timing for construction completion remains unaffected thanks to the strength and support of all contractors and stakeholders adapting to the new working environment and their seven day broken shift schedule.

The following works have been undertaken in the preceding eight weeks:

> Exposed aggregate driveways
> Joinery carcasses installed
> Internal doors installed to kitchens, bathrooms and laundries
> Concrete and acrylic render finished
> Stormwater pits and drains installed
> Block front fence and retaining walls
> Plasterboard installed
> Painting completed
> Wet areas waterproofed
> Tiling completed
> Garage doors
> Decking bearers
> Staircases
> Kitchen bulkheads
> Timber/engineered oak flooring install begins
> HVAC fit-off begins
> Electrical fit-off begins

Anticipated completion remains on track for a mid November completion/final inspection and mid December settlement.