Project Update – March 2021

Dear Ivory Purchasers,

The development team of Ivory are pleased to advise that the following works have been completed:

  • The crane has been decommissioned
  • Services layout up to the Penthouse unit is complete
  • Mechanical units and its duct works have been installed in all apartments
  • External cladding to the Western and Eastern walls are almost complete
  • Window frames installation are almost complete with the exception of front facing Livingstone Street
  • In wall electrical rough in completed up to Level 2
  • In wall plumbing for the toilet and cisterns are almost complete

Anticipated completion is due mid-September 2021.