Kirra Gardens | August 2023

Dear Kirra Gardens Purchasers,

The development team are pleased to announce that construction is progressing very well, the update as of Q3, 2023 is as followed:

The project currently sitting at 10.71% of full project completion

THE FOLLOWING SUMMARISES THE STATUS OF WORKS ON SITE:
– Bulk excavation 99% complete
– Shotcrete walls complete
– Footings complete
– In ground plumbing complete
– Basement slab 55% poured
– Basement vertical construction progressing well

KEY ACTIVITIES FOR THE COMING MONTH
– Completion of bulk excavation
– Completion of basement slab on ground
– Completion of B1 west suspended slab
– Completion of all basement walls and columns

Kind Regards,
Customer Care | Eton Property Group
customercare@etonproperty.com.au