Kirra Gardens | Q3 2023

Dear Kirra Gardens Purchasers,

The development team are pleased to announce that construction is progressing very well, the update as of Q3, 2023 is as followed:

 

The project currently sitting at 8.06% of full project completion.

 

THE FOLLOWING SUMMARISES THE STATUS OF WORKS ON SITE:

  • Bulk excavation nearing completion
  • Shotcrete walls nearing completion
  • Footings nearing completion
  • In ground plumbing progressing well

KEY ACTIVITIES FOR THE COMING MONTHS

  • Completion of bulk excavation
  • Completion of shotcrete walls
  • Completion of footings
  • Completion of inground plumbing
  • Pour of basement slab

 

Kind Regards,
Customer Care | Eton Property Group