Kirra Gardens | Q2 2023

Dear Kirra Gardens Purchasers,

The development team are pleased to announce that construction is progressing very well, the update as of Q2, 2023 is as followed:

 

The project currently sitting at 3.10% of full project completion.

 

THE FOLLOWING SUMMARISES THE STATUS OF WORKS ON SITE:

  • Site cut complete
  • Piling complete
  • Sewer tapping complete
  • Capping beam commenced
  • Bulk excavation commenced

KEY ACTIVITIES FOR THE COMING MONTHS

  • Completion of capping beam
  • Continuation of the bulk excavation
  • Commencement of shotcrete walls

 

Kind Regards,
Customer Care | Eton Property Group