Kirra Gardens | Q2 2023
Dear Kirra Gardens Purchasers,
The development team are pleased to announce that construction is progressing very well, the update as of Q2, 2023 is as followed:
The project currently sitting at 3.10% of full project completion.
THE FOLLOWING SUMMARISES THE STATUS OF WORKS ON SITE:
- Site cut complete
- Piling complete
- Sewer tapping complete
- Capping beam commenced
- Bulk excavation commenced
KEY ACTIVITIES FOR THE COMING MONTHS
- Completion of capping beam
- Continuation of the bulk excavation
- Commencement of shotcrete walls
Kind Regards,
Customer Care | Eton Property Group
customercare@etonproperty.com.au