Kirra Gardens | August 2024

Dear Kirra Gardens Purchasers,

The development team are pleased to announce that construction is progressing very well, the update as of August, 2024 is as followed:

The project currently sitting at 88.85% of full project completion

THE FOLLOWING SUMMARISES THE STATUS OF WORKS ON SITE:
– Ground works complete
– In ground plumbing complete
– Basement slab complete
– Concrete structure complete
– Services rough in complete
– Lightweight walls complete
– External planter boxes nearing completion
– External cladding complete
– Masonry install complete
– Window installation nearing completion
– Roofing complete
– Plastering complete
– Internal waterproofing nearing completion
– Internal tiling nearing completion
– Joinery proceeding well
– Painting proceeding well
– Prototype room complete
– Ground floor apartments nearing completion

KEY ACTIVITIES FOR THE COMING MONTH
Continuation of joinery
– Completion of tiling
– Continuation of painting
– Continuation of timber flooring
– Continuation of ground floor external works
– Continuation apartment handover for defecting
– Completion of footpaths and crossovers
– Completion of external civil works
– Completion of upper floor landscaping

Estimated Completion is Q4 2024.

Kind Regards,
Customer Care | Eton Property Group