Kirra Gardens | September 2024

Dear Kirra Gardens Purchasers,

The development team are pleased to announce that construction is progressing very well, the update as of September, 2024 is as followed:

The project currently sitting at 93.38% of full project completion

THE FOLLOWING SUMMARISES THE STATUS OF WORKS ON SITE:
Ground works complete
– In ground plumbing complete
– Basement slab complete
– Concrete structure complete
– Services rough in complete
– Lightweight walls complete
– External planter boxes complete
– External cladding complete
– Masonry install complete
– Window installation completion
– Roofing complete
– Plastering complete
– Internal waterproofing complete
– Internal tiling nearing completion
– Joinery nearing completion
– Painting proceeding well
– Prototype room complete
– Ground floor and level 1 apartments nearing completion
– External courtyards and fencing proceeding well
– External footpaths and crossovers complete
– External civil works complete

KEY ACTIVITIES FOR THE COMING MONTH
– Completion of joinery
– Completion of tiling
– Continuation of painting
– Completion of timber flooring
– Near completion of ground floor external works
– Continuation apartment handover for defecting
– Completion of upper floor landscaping
– Near completion of external tiling

Estimated Completion is Q4 2024.

Kind Regards,
Customer Care | Eton Property Group