Kirra Gardens | January 2024

Dear Kirra Gardens Purchasers,

Happy New Year!

The development team are pleased to announce that construction is progressing very well, the update as of January, 2024 is as followed:

The project currently sitting at 46.50% of full project completion

THE FOLLOWING SUMMARISES THE STATUS OF WORKS ON SITE:
– Ground works complete
– In ground plumbing complete
– Basement slab complete
– Concrete structure nearing complete
– Services rough in progressing
– Lightweight walls nearing completion
– External planter boxes progressing
– External cladding progressing
– Masonry install progressing
– Window installation commenced

KEY ACTIVITIES FOR THE COMING MONTH
– Completion of the lightweight structure
– Continuation of services rough in
– Continuation of partition walls
– Continuation of masonry
– Continuation of external cladding
– Continuation window install
– Commencement of roofing works

Kind Regards,
Customer Care | Eton Property Group