Kirra Gardens | Q2 2024

Dear Kirra Gardens Purchasers,

The development team are pleased to announce that construction is progressing very well, the update as of Q2, 2024 is as followed:

The project currently sitting at 66.40% of full project completion

THE FOLLOWING SUMMARISES THE STATUS OF WORKS ON SITE:
– Ground works complete
– In ground plumbing complete
– Basement slab complete
– Concrete structure complete
– Services rough in nearing completion
– Lightweight walls complete
– External planter boxes nearing completion
– External cladding nearing completion
– Masonry install nearing completion
– Window installation nearing completion
– Roofing nearing completion
– Plastering commenced
– Internal waterproofing commenced
– Internal tiling commenced

KEY ACTIVITIES FOR THE COMING MONTH
– Completion of roofing
– Completion of services rough in
– Continuation of partition walls
– Continuation of masonry
– Continuation of external cladding
– Continuation window install

Kind Regards,
Customer Care | Eton Property Group