The development team are pleased to announce that construction is progressing very well, the update as of May, 2024 is as followed:
The project currently sitting at 71.46% of full project completion
THE FOLLOWING SUMMARISES THE STATUS OF WORKS ON SITE:
– Ground works complete
– In ground plumbing complete
– Basement slab complete
– Concrete structure complete
– Services rough in nearing completion
– Lightweight walls complete
– External planter boxes nearing completion
– External cladding nearing completion
– Masonry install nearing completion
– Window installation nearing completion
– Roofing nearing completion
– Plastering proceeding well
– Internal waterproofing proceeding well
– Internal tiling proceeding well
– Joinery commenced
– Painting commenced
KEY ACTIVITIES FOR THE COMING MONTH
– Completion of roofing
– Continuation of partition walls
– Continuation of external cladding
– Continuation joinery
– Continuation of tiling
Estimated Completion is Q4 2024.