Kirra Gardens | July 2024
Dear Kirra Gardens Purchasers,
The development team are pleased to announce that construction is progressing very well, the update as of July, 2024 is as followed:
The project currently sitting at 81.62% of full project completion
THE FOLLOWING SUMMARISES THE STATUS OF WORKS ON SITE:
– Ground works complete
– In ground plumbing complete
– Basement slab complete
– Concrete structure complete
– Services rough in complete
– Lightweight walls complete
– External planter boxes nearing completion
– External cladding nearing completion
– Masonry install complete
– Window installation nearing completion
– Roofing complete
– Plastering nearing completion
– Internal waterproofing proceeding well
– Internal tiling proceeding well
– Joinery proceeding well
– Painting proceeding well
– Prototype room complete
– Ground floor apartments nearing completion
KEY ACTIVITIES FOR THE COMING MONTH
– Completion of partition walls
– Completion of external cladding
– Continuation of joinery
– Continuation of tiling
– Continuation of painting
– Continuation of timber flooring
– Continuation of ground floor external works
– Handover of ground floor apartments for defecting
Estimated Completion is Q4 2024.
Kind Regards,
Customer Care | Eton Property Group