June 2023

  • B1 suspended slab stressed and stripped
  • GF transfer slab stressed and stripped
  • Completion of L1 suspended slab
  • Commence L1 AFS vertical structural elements
  • Commence Basement soffit board installation
  • Commence B1 electrical, fire and mech high level rough in
  • Commence basement defecting

July 2023

  • Continue concrete suspended structure L2 L4
  • Continue stripping and defect rectification works B1 L2
  • Continue basement fit out works
  • Commence GF fit out works
  • Commence civil Sewer bore works

Estimated Completion is March 2024.