Dear Locale Purchasers,
The Developer’s of Locale have passed on the following updates:
June 2023
- B1 suspended slab stressed and stripped
- GF transfer slab stressed and stripped
- Completion of L1 suspended slab
- Commence L1 AFS vertical structural elements
- Commence Basement soffit board installation
- Commence B1 electrical, fire and mech high level rough in
- Commence basement defecting
July 2023
- Continue concrete suspended structure L2 L4
- Continue stripping and defect rectification works B1 L2
- Continue basement fit out works
- Commence GF fit out works
- Commence civil Sewer bore works
Estimated Completion is March 2024.
Kind Regards,
Customer Care | Eton Property Group