Neue, Highett | June 2024

Dear Neue Purchasers,

Please find the following updates below from the builders on-site:

APARTMENTS

  • Footpath complete
  • Crossover + Curb and Channel complete
  • External Landscaping commenced
  • Painting – All corridor walls completed
  • Painting – Level 3 Final painting completed
  • Painting – Level 2 Final Painting completed
  • Painting – GF Final Painting completed to 16/19 apartments
  • Tiling- Only Ground Floor Pod and Paver outstanding
  • Tiling – Ground Floor Lobby/Corridor tiling outstanding
  • Joinery- completed
  • Screens –  90% Bedroom Robes installed
  • Screens – 90% Shower screens installed
  • Splashbacks- 100% Splashback installed
  • Stone – Install complete
  • Wet Fire  – Commissioning to Pump Room and Booster cupboard outstanding
  • Mechanical – Indoor split system fit off completed
  • Hydraulic – 100% of fit-off complete
  • Floor Preparation – Floor grind and Self Levelling 100% complete
  • Floor Coverings – Level 1 – 100% complete
  • Floor Coverings – Level 2 – 100% complete
  • Floor Coverings – Level 3 – 100% complete
  • Floor Coverings – Ground Floor – 17/19 complete
  • Balustrading – 100% complete
  • Storage – Storage Cage install complete
  • Storage – Storage Cage doors outstanding
  • Appliances – Level 3 Appliance Install complete
  • Appliances – Level 2 Appliance Install complete
  • Appliances – Level 1 Appliance Install complete
  • Appliances – Ground Floor Appliance Install complete 17/19

TOWNHOMES

  • Roofing 100% complete
  • Painting completed to Townhouse
  • Insulation installed to all Townhouses
  • Plasterboard install complete
  • Carpentry First Fix commenced
  • Townhouse Scaffold dismantled

 

The estimated practical completion is July with settlements expected in July/August.

Kind Regards,
Customer Care | Eton Property Group