Neue, Highett | June 2024
Dear Neue Purchasers,
Please find the following updates below from the builders on-site:
APARTMENTS
- Footpath complete
- Crossover + Curb and Channel complete
- External Landscaping commenced
- Painting – All corridor walls completed
- Painting – Level 3 Final painting completed
- Painting – Level 2 Final Painting completed
- Painting – GF Final Painting completed to 16/19 apartments
- Tiling- Only Ground Floor Pod and Paver outstanding
- Tiling – Ground Floor Lobby/Corridor tiling outstanding
- Joinery- completed
- Screens – 90% Bedroom Robes installed
- Screens – 90% Shower screens installed
- Splashbacks- 100% Splashback installed
- Stone – Install complete
- Wet Fire – Commissioning to Pump Room and Booster cupboard outstanding
- Mechanical – Indoor split system fit off completed
- Hydraulic – 100% of fit-off complete
- Floor Preparation – Floor grind and Self Levelling 100% complete
- Floor Coverings – Level 1 – 100% complete
- Floor Coverings – Level 2 – 100% complete
- Floor Coverings – Level 3 – 100% complete
- Floor Coverings – Ground Floor – 17/19 complete
- Balustrading – 100% complete
- Storage – Storage Cage install complete
- Storage – Storage Cage doors outstanding
- Appliances – Level 3 Appliance Install complete
- Appliances – Level 2 Appliance Install complete
- Appliances – Level 1 Appliance Install complete
- Appliances – Ground Floor Appliance Install complete 17/19
TOWNHOMES
- Roofing 100% complete
- Painting completed to Townhouse
- Insulation installed to all Townhouses
- Plasterboard install complete
- Carpentry First Fix commenced
- Townhouse Scaffold dismantled
The estimated practical completion is July with settlements expected in July/August.
Kind Regards,
Customer Care | Eton Property Group