Neue, Highett | May 2024
Dear Neue Purchasers,
Please find the following updates below from the builders on-site:
APARTMENTS
- Carpentry – All service cupboard door hardware installed
- Carpentry – Level 1 Carpentry Final Fix/Fit-off 100% complete
- Carpentry – Level 2 Carpentry Final Fix/Fit-off 100% complete
- Carpentry – Level 3 Carpentry Final Fix/Fit-off 100% complete
- Carpentry – Ground Floor Carpentry Final Fix/Fit-off 100% complete
- Carpentry – Common Area/ Corridor Skirting completed
- Carpentry – Bathroom fixture install complete
- Painting – All internal painting completed to apartments from level 3 to Ground Floor
- Painting – Hoist apartments and Catch up units above the ramp have been completed final coats (only 1 coat walls remaining once fix is completed)
- Painting – All corridor ceilings have been completed
- Painting – All corridor walls require 1 coat of paint
- Painting – External Ground Floor painting complete
- Painting – Level 3 Final painting commenced
- Painting – Level 1 Final Painting complete
- Painting – Level 2 Final Painting complete to 16/22 apartments
- Painting – GF Final Painting commencing 20/05
- Tiling- Only Ground Floor Pod and Paver outstanding
- Tiling – Ground Floor Lobby/Corridor tiling outstanding
- Electrical – Electrical rough in completed
- Electrical – Corridor and Lobby Fit-off completed
- Electrical – Final apartment fit-off commenced
- Joinery- Ground – 19/19 completed
- Joinery –Level 1 – 20/22 completed
- Joinery –Level 2 – 20/22 completed
- Joinery –Level 3 – 11/11 completed
- Screens – Shower screens all installed on Ground Floor
- Screens – Shower screen install commenced on Level 1
- Screens- Splashbacks installed on Ground Floor 16/19 complete
- Screens – Splashbacks installed on Level 1 10/22 complete
- Screens- Brackets for front façade screens installed
- Robe – Robe install commenced on Level 1
- Stone – Install continued on Level 1 – 95% complete
- Stone – Install continued on Ground Floor – approximately 90 % complete
- Stone – Install on Level 2 commenced – 75% complete
- Stone – Install on Level 3 – 75% complete
- Wet Fire – Commissioning to Pump Room and Booster cupboard outstanding
- Mechanical – Indoor split system fit off commenced Level 3 to Ground Floor
- Mechanical – Indoor split system fit off commenced Level 2 to Ground Floor
- Mechanical – Indoor split system fit off commenced Level 1 to Ground Floor
- Mechanical – Carpark duct works continued 100% complete
- Hydraulic – 100% of rough in complete to apartments
- Hydraulic- Storm Water connection works completed
- Hydraulic – Water Main connection works completed
- Hydraulic – Level 1 apartment fit off complete
- Hydraulic- Level 2 apartment fit off complete
- Floor Preparation – Floor grind and Self Levelling on Level 1 100% complete
- Floor Preparation – Floor grinding and Self Levelling on Level 2 75% complete
- Floor Coverings – Level 1 – Timber flooring complete
- Floor Coverings – Level 2 – Timber flooring 16/22 complete
- Floor Coverings – Level 3 – Timber flooring complete
- Floor Coverings – Ground Floor – 6/19 complete
- Vertical Transportation – Lift 2 install complete
- Vertical Transportation – Lift installation complete for project
- Balustrading – Glass installed to 75% of Level 3 balconies
- Storage – Storage Cage install completed
- Screens – Feature Screens installed to Front Façade
- Appliances – Appliance Fit-off commenced on Level 1
The estimated practical completion is June 2024.
Kind Regards,
Customer Care | Eton Property Group
customercare@etonproperty.com.au