Neue, Highett | May 2024

Dear Neue Purchasers,

Please find the following updates below from the builders on-site:

APARTMENTS

  • Carpentry –  All service cupboard door hardware installed
  • Carpentry – Level 1 Carpentry Final Fix/Fit-off 100% complete
  • Carpentry – Level 2 Carpentry Final Fix/Fit-off 100% complete
  • Carpentry – Level 3 Carpentry Final Fix/Fit-off 100% complete
  • Carpentry – Ground Floor Carpentry Final Fix/Fit-off 100% complete
  • Carpentry – Common Area/ Corridor Skirting completed
  • Carpentry – Bathroom fixture install complete
  • Painting – All internal painting completed to apartments from level 3 to Ground Floor
  • Painting – Hoist apartments and Catch up units above the ramp have been completed final coats (only 1 coat walls remaining once fix is completed)
  • Painting – All corridor ceilings have been completed
  • Painting – All corridor walls require 1 coat of paint
  • Painting – External Ground Floor painting complete
  • Painting – Level 3 Final painting commenced
  • Painting – Level 1 Final Painting complete
  • Painting – Level 2 Final Painting complete to 16/22 apartments
  • Painting – GF Final Painting commencing 20/05
  • Tiling- Only Ground Floor Pod and Paver outstanding
  • Tiling – Ground Floor Lobby/Corridor tiling outstanding
  • Electrical – Electrical rough in completed
  • Electrical – Corridor and Lobby Fit-off completed
  • Electrical – Final apartment fit-off commenced
  • Joinery- Ground – 19/19 completed
  • Joinery –Level 1 – 20/22 completed
  • Joinery –Level 2 – 20/22 completed
  • Joinery –Level 3 – 11/11 completed
  • Screens –  Shower screens all installed on Ground Floor
  • Screens – Shower screen install commenced on Level 1
  • Screens- Splashbacks installed on Ground Floor 16/19 complete
  • Screens – Splashbacks installed on Level 1 10/22 complete
  • Screens- Brackets for front façade screens installed
  • Robe – Robe install commenced on Level 1
  • Stone – Install continued on Level 1 – 95% complete
  • Stone –  Install continued on Ground Floor – approximately 90 % complete
  • Stone – Install on Level 2 commenced – 75% complete
  • Stone – Install on Level 3 – 75% complete
  • Wet Fire  – Commissioning to Pump Room and Booster cupboard outstanding
  • Mechanical – Indoor split system fit off commenced Level 3 to Ground Floor
  • Mechanical – Indoor split system fit off commenced Level 2 to Ground Floor
  • Mechanical – Indoor split system fit off commenced Level 1 to Ground Floor
  • Mechanical – Carpark duct works continued 100% complete
  • Hydraulic – 100% of rough in complete to apartments
  • Hydraulic- Storm Water connection works completed
  • Hydraulic – Water Main connection works completed
  • Hydraulic – Level 1 apartment fit off complete
  • Hydraulic- Level 2 apartment fit off complete
  • Floor Preparation – Floor grind and Self Levelling on Level 1 100% complete
  • Floor Preparation – Floor grinding and Self Levelling on Level 2 75% complete
  • Floor Coverings – Level 1 – Timber flooring complete
  • Floor Coverings – Level 2 – Timber flooring 16/22 complete
  • Floor Coverings – Level 3 – Timber flooring complete
  • Floor Coverings – Ground Floor – 6/19 complete
  • Vertical Transportation –  Lift 2 install complete
  • Vertical Transportation – Lift installation complete for project
  • Balustrading – Glass installed to 75% of Level 3 balconies
  • Storage – Storage Cage install completed
  • Screens –  Feature Screens installed to Front Façade
  • Appliances – Appliance Fit-off commenced on Level 1

The estimated practical completion is June 2024.

Kind Regards,
Customer Care | Eton Property Group