Neue, Highett | Q2 2024
Dear Neue Purchasers,
Please find the following updates below from the builders on-site:
CARPENTRY
- Carpentry – All service cupboard doors installed
- Carpentry – Level 1 Carpentry Final Fix/Fit-off 100% complete
- Carpentry – Level 2 Carpentry Final Fix/Fit-off 70% complete
- Carpentry – Level 3 Carpentry Final Fix/Fit-off 70% complete
- Carpentry – Ground Floor Carpentry Final Fix/Fit-off 50% complete
- Carpentry – Common Area/ Corridor Skirting completed
- Carpentry – Bathroom fixture install complete
PAINTING
- Painting – All internal painting completed to apartments from level 3 to Ground Floor
- Painting – Hoist apartments and Catch up units above the ramp have been completed final coats (only 1 coat walls remaining once fix is completed)
- Painting – All corridor ceilings have been completed
- Painting – All corridor walls require 1 coat of paint
- Painting – All external painting completed
- Painting – External Ground Floor painting 75% complete
TILING
- Tiling- Internal Apartment tiling completed
- Tiling – Pod and Paver install complete on Level 1,2 and 3
- Tiling – Feature Tiling to Lift completed Level 1, 2 and 3
- Tiling- Only Ground Floor Pod and Paver outstanding
WATERPROOFING
- Waterproofing – External waterproofing to balconies and pebbled areas completed
- Waterproofing – Level 1,2 and 3 balcony waterproofing completed
FRAMING/PLASTERING
- Framing/Plastering – All internal framing and plastering completed
CLADDING/SHROUDS
- Cladding/Shrouds – Cladding on Level 3 (100% complete)
- Cladding/Shrouds- External shrouds (100% complete)
- Cladding/Shrouds- Cladding on Ramp 100% complete
ELECTRICAL
- Electrical – Electrical rough in completed
- Electrical – Corridor and Lobby Fit-off completed
- Electrical – Final apartment fit-off commenced
JOINERY
- Joinery- Ground – 19/19 completed
- Joinery –Level 1 – 20/22 completed
- Joinery –Level 2 – 20/22 completed
- Joinery –Level 3 – 11/11 completed
SPLASHBACKS/SCREENS/ROBE’S
- Screens – Shower screens all installed on Ground Floor
- Screens – Shower screen install commenced on Level 1
- Screens- Splashbacks installed on Ground Floor 16/19 complete
- Screens – Splashbacks installed on Level 1 10/22 complete
- Screens- Brackets for front façade screens installed
- Robe – Robe install commenced on Level 1
STONE
- Stone – Install continued on Level 1 – 95% complete
- Stone – Install continued on Ground Floor – approximately 90 % complete
- Stone – Install on Level 2 commenced
WET FIRE
- Wet Fire – Basement fire sprinkler install 100% completed
- Wet Fire- Sprinkler Dropper complete Level 3
- Wet Fire – Test Drain installed in Stairwell 2
- Wet Fire- Fire Hydrant and Fire Sprinkler Mains installed
- Wet Fire – Hydrant and Booster Mains Works connection completed
MECHANICAL
- Mechanical – Indoor split system fit off commenced Level 3 to Ground Floor
- Mechanical – Indoor split system fit off commenced Level 2 to Ground Floor
- Mechanical – Indoor split system fit off commenced Level 1 to Ground Floor
- Mechanical – Carpark duct works continued 100% complete
HYDRAULIC
- Hydraulic – 100% of rough in complete to apartments
- Hydraulic- Storm Water connection works completed
- Hydraulic – Water Main connection works completed
- Hydraulic – Level 1 apartment fit off complete
- Hydraulic- Level 2 apartment fit off complete
FLOOR PREPARATION
- Floor Preparation – Floor grind and Self Levelling on Level 1 100% complete
- Floor Preparation – Floor grinding and Self Levelling on Level 2 75% complete
FLOOR COVERINGS
- Floor Coverings – Level 1 – Timber flooring complete
- Floor Coverings – Level 2 – Timber flooring 16/22 complete
- Floor Coverings – Level 3 – 7/11 complete
- Floor Coverings – Ground Floor – 6/19 complete
VERTICAL TRANSPORTATION
- Vertical Transportation – Lift 2 works starting 2nd week of March
ROOFING
- Roofing – All Roofing has been completed
- Roofing – Capping’s and Flashings 100% complete
BALUSTRADING
- Balustrading – All balustrade channels have been installed on Level 3 now waiting for glass install
SCAFFOLDING
- Scaffolding – All perimeter scaffold has been removed from Apartments
STORAGE CAGES
- Storage – Storage Cage install started and due to be completed by 19/04
PLUMBING
- Stormwater – Stormwater connection completed
- Gas – Gas connection completed
- Water – Water Main connection completed
The anticipated practical completion is mid June with settlements estimated in July.
TOWNHOMES:
- All services rough in completed
- Solar and Hot Water Services installed to Main Roof
- Internal Framing completed
- Cladding 95% complete
- Roofing 95% complete
- Painting completed to Townhouse
- Insulation installed to all Townhouses
Kind Regards,