Neue, Highett | Q2 2024

Dear Neue Purchasers,

Please find the following updates below from the builders on-site:

CARPENTRY

  •  Carpentry –  All service cupboard doors installed
  • Carpentry – Level 1 Carpentry Final Fix/Fit-off 100% complete
  • Carpentry – Level 2 Carpentry Final Fix/Fit-off 70% complete
  • Carpentry – Level 3 Carpentry Final Fix/Fit-off 70% complete
  • Carpentry – Ground Floor Carpentry Final Fix/Fit-off 50% complete
  • Carpentry – Common Area/ Corridor Skirting completed
  • Carpentry – Bathroom fixture install complete

PAINTING

  • Painting – All internal painting completed to apartments from level 3 to Ground Floor
  • Painting – Hoist apartments and Catch up units above the ramp have been completed final coats (only 1 coat walls remaining once fix is completed)
  • Painting – All corridor ceilings have been completed
  • Painting – All corridor walls require 1 coat of paint
  • Painting – All external painting completed
  • Painting – External Ground Floor painting 75% complete

TILING

  • Tiling- Internal Apartment tiling completed
  • Tiling – Pod and Paver install complete on Level 1,2 and 3
  • Tiling – Feature Tiling to Lift completed Level 1, 2 and 3
  • Tiling- Only Ground Floor Pod and Paver outstanding

WATERPROOFING

  • Waterproofing – External waterproofing to balconies and pebbled areas completed
  • Waterproofing – Level 1,2 and 3 balcony waterproofing completed

FRAMING/PLASTERING

  • Framing/Plastering – All internal framing and plastering completed

CLADDING/SHROUDS

  • Cladding/Shrouds – Cladding on Level 3 (100% complete)
  • Cladding/Shrouds- External shrouds (100% complete)
  • Cladding/Shrouds- Cladding on Ramp 100% complete

ELECTRICAL

  • Electrical – Electrical rough in completed
  • Electrical – Corridor and Lobby Fit-off completed
  • Electrical – Final apartment fit-off commenced

JOINERY

  • Joinery- Ground – 19/19 completed
  • Joinery –Level 1 – 20/22 completed
  • Joinery –Level 2 – 20/22 completed
  • Joinery –Level 3 – 11/11 completed

SPLASHBACKS/SCREENS/ROBE’S

  • Screens –  Shower screens all installed on Ground Floor
  • Screens – Shower screen install commenced on Level 1
  • Screens- Splashbacks installed on Ground Floor 16/19 complete
  • Screens – Splashbacks installed on Level 1 10/22 complete
  • Screens- Brackets for front façade screens installed
  • Robe – Robe install commenced on Level 1

STONE

  • Stone – Install continued on Level 1 – 95% complete
  • Stone –  Install continued on Ground Floor – approximately 90 % complete
  • Stone – Install on Level 2 commenced

WET FIRE

  • Wet Fire  – Basement fire sprinkler install 100% completed
  • Wet Fire- Sprinkler Dropper complete Level 3
  • Wet Fire –  Test Drain installed in Stairwell 2
  • Wet Fire- Fire Hydrant and Fire Sprinkler Mains installed
  • Wet Fire –  Hydrant and Booster Mains Works connection completed

MECHANICAL

  • Mechanical – Indoor split system fit off commenced Level 3 to Ground Floor
  • Mechanical – Indoor split system fit off commenced Level 2 to Ground Floor
  • Mechanical – Indoor split system fit off commenced Level 1 to Ground Floor
  • Mechanical – Carpark duct works continued 100% complete

HYDRAULIC

  • Hydraulic – 100% of rough in complete to apartments
  • Hydraulic- Storm Water connection works completed
  • Hydraulic – Water Main connection works completed
  • Hydraulic – Level 1 apartment fit off complete
  • Hydraulic- Level 2 apartment fit off complete

FLOOR PREPARATION

  • Floor Preparation – Floor grind and Self Levelling on Level 1 100% complete
  • Floor Preparation – Floor grinding and Self Levelling on Level 2 75% complete

FLOOR COVERINGS

  • Floor Coverings – Level 1 – Timber flooring complete
  • Floor Coverings – Level 2 – Timber flooring 16/22 complete
  • Floor Coverings – Level 3 – 7/11 complete
  • Floor Coverings – Ground Floor – 6/19 complete

VERTICAL TRANSPORTATION

  • Vertical Transportation –  Lift 2 works starting 2nd week of March

ROOFING

  • Roofing – All Roofing has been completed
  • Roofing – Capping’s and Flashings 100% complete

BALUSTRADING

  • Balustrading – All balustrade channels have been installed on Level 3 now waiting for glass install

SCAFFOLDING

  • Scaffolding – All perimeter scaffold has been removed from Apartments

STORAGE CAGES

  • Storage – Storage Cage install started and due to be completed by 19/04

PLUMBING

  • Stormwater – Stormwater connection completed
  • Gas – Gas connection completed
  • Water –  Water Main connection completed

 

The anticipated practical completion is mid June with settlements estimated in July.

 

TOWNHOMES:

  • All services rough in completed
  • Solar and Hot Water Services installed to Main Roof
  • Internal Framing completed
  • Cladding 95% complete
  • Roofing 95% complete
  • Painting completed to Townhouse
  • Insulation installed to all Townhouses

 

Kind Regards,
Customer Care | Eton Property Group