Neue, Highett | March 2024

Dear Neue Purchasers,

Please find the following updates below from the builders on-site:

  • Carpentry –  Level 3 entry door installed and fitted off
  • Carpentry – Door Hardware fit off on Level 3 and 2 complete
  • Carpentry – Skirting to timber floor commencing
  • Carpentry – Bathroom fixture install commencing
  • Painting – All internal painting completed to apartments from level 3 to Ground Floor
  • Painting – Only hoist apartments remaining for Second Coat on Ground Floor
  • Painting – All external painting completed except Ground Floor
  • Tiling – Level 3 – All apartments complete
  • Tiling – Level 2 – 21/22 apartments complete
  • Tiling – Level 1 – All apartments complete
  • Tiling – Ground Floor – 19/20 apartments complete
  • Tiling – Pod and Paver install complete on Level 1 and Level 2 balconies
  • Tiling – Pod and Paver install 75% complete on Level 3
  • Waterproofing – External waterproofing to balconies and pebbled areas commencing
  • Waterproofing – Level 1,2 and 3 balcony waterproofing complete
  • Framing/Plastering – All internal framing and plastering completed

The anticipated practical completion is May with settlement expected in June.

Kind Regards,
Customer Care | Eton Property Group