Neue, Highett | March 2024
Dear Neue Purchasers,
Please find the following updates below from the builders on-site:
- Carpentry – Level 3 entry door installed and fitted off
- Carpentry – Door Hardware fit off on Level 3 and 2 complete
- Carpentry – Skirting to timber floor commencing
- Carpentry – Bathroom fixture install commencing
- Painting – All internal painting completed to apartments from level 3 to Ground Floor
- Painting – Only hoist apartments remaining for Second Coat on Ground Floor
- Painting – All external painting completed except Ground Floor
- Tiling – Level 3 – All apartments complete
- Tiling – Level 2 – 21/22 apartments complete
- Tiling – Level 1 – All apartments complete
- Tiling – Ground Floor – 19/20 apartments complete
- Tiling – Pod and Paver install complete on Level 1 and Level 2 balconies
- Tiling – Pod and Paver install 75% complete on Level 3
- Waterproofing – External waterproofing to balconies and pebbled areas commencing
- Waterproofing – Level 1,2 and 3 balcony waterproofing complete
- Framing/Plastering – All internal framing and plastering completed
The anticipated practical completion is May with settlement expected in June.
Kind Regards,
Customer Care | Eton Property Group