Neue, Highett | January 2024
Dear Neue Purchasers,
Please find the following updates below from the builders on-site:
APARTMENTS:
- Carpentry – Ground Floor first fix complete (internal door + door jamb, bedroom skirting, robes and architraves)
- Carpentry – Level 1 first fix complete (internal door + door jamb, bedroom skirting, robes and architraves)
- Carpentry – Level 2 first fix complete (internal door + door jamb, bedroom skirting, robes and architraves)
- Carpentry – Level 3 first fix complete (internal door + door jamb, bedroom skirting, robes and architraves)
- Painting – Level 3 sealer coats all complete
- Painting – Only hoist apartments remaining for sealer coats
- Tiling- Level 3 – 10/11 apartments complete
- Tiling – Level 2 – 20/22 apartments complete
- Tiling – Level 1 – 20/22 apartments complete
- Tiling – Ground Floor – 17/20 apartments complete
- Waterproofing – External waterproofing to balconies and pebbled areas commencing
- Framing/Plastering – All internal framing completed
- Plastering – Patching and Sanding to Hoist apartments and corridors complete
- Cladding/Shrouds – Cladding on Level 3 (80% complete) waiting on flashings for roof to complete remaining works
- Cladding/Shrouds- External shrouds (90% complete) waiting on scaffold drop to complete remaining install
- Cladding/Shrouds- Cladding on Ramp 75% complete
- Cladding/Shrouds – Cladding above apartment 217 in South East 95% completed
- Electrical – Level 2 Fit off continued
- Joinery – Joinery install started on Level 1 – approximately 50% complete
- Joinery – Joinery install started on Level 2 – approximately 50% complete
- Screens – Shower screens all measured on Ground Floor and Level 1
- Stone – Install started on Level 1 – approximately 90% complete
- Wet Fire – Basement fire sprinkler install 90% completed
- Wet Fire- Sprinkler Dropper install started on Level 3
- Dry Fire – Smoke door frames installed
- Dry Fire – All rough in works completed
- Windows/Glass- Window install completed
- Mechanical – 100% of rough in complete to apartments
- Hydraulic – 100% of rough in complete to apartments
- Floor Preparation – Floor grind and Self Levelling on Level 1 90% complete
- Floor Preparation – Floor grinding and Self Levelling on Level 2 75% complete
- Vertical Transportation – Builders Lift commissioned and fully operational
- Vertical Transportation – Lift 2 works yet to be continued
- Roofing – All Roofing has been completed
- Roofing – Capping’s and Flashings to balconies 90% complete
- Balustrading – Channels have been installed to Level 3 balconies
- Scaffolding – All Scaffolding has been removed from North East Elevation (Nepean Highway side)
TOWNHOUSES:
- Window Installation completed
- Cladding Batten install commenced 100% complete
- Mechanical rough in commenced 100% complete
- Hydraulic rough in commenced 90% complete
- Electrical rough in commencing 95% complete
- Main Roof capping’s completed to main roof
- Roof Hatch install complete
- Roof penetrations complete
- Cladding install continued 75% complete
- Entry door frames installed
- Shrouds installed
The anticipated practical completion is April 2024.
Kind Regards,
Customer Care | Eton Property Group