Neue, Highett | January 2024

Dear Neue Purchasers,

Please find the following updates below from the builders on-site:

APARTMENTS:

  • Carpentry – Ground Floor first fix complete (internal door + door jamb, bedroom skirting, robes and architraves)
  • Carpentry – Level 1 first fix complete (internal door + door jamb, bedroom skirting, robes and architraves)
  • Carpentry – Level 2 first fix complete (internal door + door jamb, bedroom skirting, robes and architraves)
  • Carpentry – Level 3 first fix complete (internal door + door jamb, bedroom skirting, robes and architraves)
  • Painting – Level 3 sealer coats all complete
  • Painting – Only hoist apartments remaining for sealer coats
  • Tiling- Level 3 – 10/11 apartments complete
  • Tiling – Level 2 – 20/22 apartments complete
  • Tiling – Level 1 – 20/22 apartments complete
  • Tiling – Ground Floor – 17/20 apartments complete
  • Waterproofing – External waterproofing to balconies and pebbled areas commencing
  • Framing/Plastering – All internal framing completed
  • Plastering – Patching and Sanding to Hoist apartments and corridors complete
  • Cladding/Shrouds – Cladding on Level 3 (80% complete) waiting on flashings for roof to complete remaining works
  • Cladding/Shrouds- External shrouds (90% complete) waiting on scaffold drop to complete remaining install
  • Cladding/Shrouds- Cladding on Ramp 75% complete
  • Cladding/Shrouds – Cladding above apartment 217 in South East 95% completed
  • Electrical – Level 2 Fit off continued
  • Joinery – Joinery install started on Level 1 – approximately 50% complete
  • Joinery – Joinery install started on Level 2 – approximately 50% complete
  • Screens –  Shower screens all measured on Ground Floor and Level 1
  • Stone – Install started on Level 1 – approximately 90% complete
  • Wet Fire  – Basement fire sprinkler install 90% completed
  • Wet Fire- Sprinkler Dropper install started on Level 3
  • Dry Fire – Smoke door frames installed
  • Dry Fire – All rough in works completed
  • Windows/Glass- Window install completed
  • Mechanical – 100% of rough in complete to apartments
  • Hydraulic – 100% of rough in complete to apartments
  • Floor Preparation – Floor grind and Self Levelling on Level 1 90% complete
  • Floor Preparation – Floor grinding and Self Levelling on Level 2 75% complete
  • Vertical Transportation – Builders Lift commissioned and fully operational
  • Vertical Transportation –  Lift 2 works yet to be continued
  • Roofing – All Roofing has been completed
  • Roofing – Capping’s and Flashings to balconies 90% complete
  • Balustrading – Channels have been installed to Level 3 balconies
  • Scaffolding – All Scaffolding has been removed from North East Elevation (Nepean Highway side)

 

TOWNHOUSES:

  • Window Installation completed
  • Cladding Batten install commenced 100% complete
  • Mechanical rough in commenced 100% complete
  • Hydraulic rough in commenced  90% complete
  • Electrical rough in commencing 95% complete
  • Main Roof capping’s completed to main roof
  • Roof Hatch install complete
  • Roof penetrations complete
  • Cladding install continued 75% complete
  • Entry door frames installed
  • Shrouds installed

 

The anticipated practical completion is April 2024.

 

Kind Regards,
Customer Care | Eton Property Group