Neue, Highett | December 2023
Dear Neue Purchasers,
Please find the following updates below from the builders on-site:
- Carpentry – Level 2 entry doors all installed and hardware fitted off
- Carpentry – Level 1 internal door hardware all complete
- Carpentry – Level 1 skirting started to carpeted bedrooms
- Carpentry – Level 2 internal door hardware fit off started
- Carpentry – Ground Floor Apartment skirting started to carpeted bedrooms completed
- Painting – Level 2 entry doors Sealer coat and First Coat has been applied
- Painting – External Cladding and Wall Paint 95% completed
- Painting – Painting to catch up apartments on Level 2 commencing 6/12
- Tiling – Wall tiling continued 95% complete on Level 1
- Waterproofing – Level 2 Bathroom and Ensuite tanking has commenced
- Framing/Plastering – Level 3 Apartment Plasterboard Wall Hanging completed
- Framing/Plastering – Level 3 Plaster Stopping commenced and will be completed by 11/12
- Framing/Plastering – All corridor Ceiling grid framing completed
- Framing/Plastering – All corridor ceilings have been sheeted and stopping commenced
- Framing/Plastering – All framing, plaster hanging and stopping to catch up apartments above ramp have now been completed
- Cladding/Shrouds – Cladding on Level 3 (80% complete) waiting on flashings for roof to complete remaining works
- Cladding/Shrouds – External shrouds (90% complete) waiting on scaffold drop to complete remaining install
- Cladding/Shrouds – Cladding on Ramp 75% complete
- Cladding/Shrouds – Cladding above apartment 217 in South East 95% completed
- Electrical – Level 2 Fit off continued
- Joinery – Joinery installed from apartment 118-122
- Wet Fire – Basement fire sprinkler install 90% completed
- Wet Fire- Sprinkler Dropper install started on Level 3
- Dry Fire – Speakers on L1 and L2 fitted off
- Dry Fire – Rough in Level 1 -3 (95% complete)
- Windows/Glass- Windows installed completed only Hoist apartments remaining G07, G08, 109, 110, 209, 210
- Mechanical – 100% of rough in complete to apartments
- Hydraulic – 95% of rough in complete to apartments only Hoist Apartments remaining on each Level
- Floor Preparation – Floor grind and Self Levelling on Level 1 80% complete
- Floor Preparation – Floor grinding and Self Levelling on Level 2 50% complete
- Vertical Transportation – Lift 1 install completed
- Vertical Transportation – Lift 2 install completed
- Vertical Transportation – Lift commissioning and Handover booked for 6/12
- Roofing – Flashing and Capping install 85% completed for Level 3 No further progress made on balustrading
- Scaffolding – Scaffolding removed from Ramp to Hoist
- Material Hoist – Material Hoist removed
The anticipated practical completion is March – April 2024.
Kind Regards,
Customer Care | Eton Property Group