Neue, Highett | December 2023

Dear Neue Purchasers,

Please find the following updates below from the builders on-site:

  • Carpentry – Level 2 entry doors all installed and hardware fitted off
  • Carpentry – Level 1 internal door hardware all complete
  • Carpentry – Level 1 skirting started to carpeted bedrooms
  • Carpentry – Level 2 internal door hardware fit off started
  • Carpentry – Ground Floor Apartment skirting started to carpeted bedrooms completed
  • Painting – Level 2 entry doors Sealer coat and First Coat has been applied
  • Painting – External Cladding and Wall Paint 95% completed
  • Painting – Painting to catch up apartments on Level 2 commencing 6/12
  • Tiling – Wall tiling continued 95% complete on Level 1
  • Waterproofing – Level 2 Bathroom and Ensuite tanking has commenced
  • Framing/Plastering – Level 3 Apartment Plasterboard Wall Hanging completed
  • Framing/Plastering – Level 3 Plaster Stopping commenced and will be completed by 11/12
  • Framing/Plastering – All corridor Ceiling grid framing completed
  • Framing/Plastering – All corridor ceilings have been sheeted and stopping commenced
  • Framing/Plastering – All framing, plaster hanging and stopping to catch up apartments above ramp have now been completed
  • Cladding/Shrouds – Cladding on Level 3 (80% complete) waiting on flashings for roof to complete remaining works
  • Cladding/Shrouds – External shrouds (90% complete) waiting on scaffold drop to complete remaining install
  • Cladding/Shrouds – Cladding on Ramp 75% complete
  • Cladding/Shrouds – Cladding above apartment 217 in South East 95% completed
  • Electrical – Level 2 Fit off continued
  • Joinery – Joinery installed from apartment 118-122
  • Wet Fire – Basement fire sprinkler install 90% completed
  • Wet Fire- Sprinkler Dropper install started on Level 3
  • Dry Fire – Speakers on L1 and L2 fitted off
  • Dry Fire – Rough in Level 1 -3 (95% complete)
  • Windows/Glass- Windows installed completed only Hoist apartments remaining G07, G08, 109, 110, 209, 210
  • Mechanical – 100% of rough in complete to apartments
  • Hydraulic – 95% of rough in complete to apartments only Hoist Apartments remaining on each Level
  • Floor Preparation – Floor grind and Self Levelling on Level 1 80% complete
  • Floor Preparation – Floor grinding and Self Levelling on Level 2 50% complete
  • Vertical Transportation – Lift 1 install completed
  • Vertical Transportation – Lift 2 install completed
  • Vertical Transportation – Lift commissioning and Handover booked for 6/12
  • Roofing – Flashing and Capping install 85% completed for Level 3 No further progress made on balustrading
  • Scaffolding – Scaffolding removed from Ramp to Hoist
  • Material Hoist – Material Hoist removed

The anticipated practical completion is March – April 2024.