Neue, Highett | August 2023

Dear Neue Purchasers,

Please find the following updates below from the builders on-site:

Apartments:

  • Electrical – starting cut outs and striping on level 1 and 2 – will be ongoing scope
  • Ground floor 1st fix completed, entry door to apart. Will be ongoing scope
  • Level 1 1st fix – ongoing scope
  • Internal plaster defects on level 1
  • Plaster stopping have started on level 2 and will be ongoing
  • Ground floor Kitchen – installation complete ( except on apart not built )
  • Internal paint – base coat on level 1, level 2 will roll to next month
  • Internal light court door installed – this area is 100% completed
  • Lifts installation will roll to next month
  • Roofing works to lower roofs structure, completed ( south )
  • External waterproof membranes to lifts over run is complete
  • External framing for cladding for balconies completed on all levels.
  • External claddings (linings) in progress
  • External paint – started , ongoing scope ( half of the building is completed )
  • External shrouds and screening commenced and will be ongoing.
  • All pre-cast panels installed
  • All works for super-structure 100% completed
  • Electrical works to obtain permanent power – on going
    Level 3 scaffold – dismantled

Townhouses:

  • Metal structure – on going scope
  • Framing – ground level completed
  • Framing – level 1 will roll to next month
  • Electrical – mains are installed

The estimated practical completion for apartment is around end of Nov to Dec 2023.

Kind Regards,
Customer Care | Eton Property Group