Dear Neue Purchasers,
Please find the following updates below from the builders on-site:
Apartments:
- Electrical – starting cut outs and striping on level 1 and 2 – will be ongoing scope
- Ground floor 1st fix completed, entry door to apart. Will be ongoing scope
- Level 1 1st fix – ongoing scope
- Internal plaster defects on level 1
- Plaster stopping have started on level 2 and will be ongoing
- Ground floor Kitchen – installation complete ( except on apart not built )
- Internal paint – base coat on level 1, level 2 will roll to next month
- Internal light court door installed – this area is 100% completed
- Lifts installation will roll to next month
- Roofing works to lower roofs structure, completed ( south )
- External waterproof membranes to lifts over run is complete
- External framing for cladding for balconies completed on all levels.
- External claddings (linings) in progress
- External paint – started , ongoing scope ( half of the building is completed )
- External shrouds and screening commenced and will be ongoing.
- All pre-cast panels installed
- All works for super-structure 100% completed
- Electrical works to obtain permanent power – on going
Level 3 scaffold – dismantled
Townhouses:
- Metal structure – on going scope
- Framing – ground level completed
- Framing – level 1 will roll to next month
- Electrical – mains are installed
The estimated practical completion for apartment is around end of Nov to Dec 2023.
Kind Regards,
Customer Care | Eton Property Group