Neue, Highett | Q3 2023

Dear Neue Purchasers,

Please find the following updates below from the builders on-site:

  • Internal services (Electrical) Mains completed, starting cut outs and striping on  level 1 and 2 – will be ongoing scope
  • Ground floor 1st fix started, ongoing scope
  • Roofing works to lower roofs structure, completed this month (south)
  • Internal plaster sheeting has been started on L2, ceilings follow progressively
  • Plaster stopping have started on level 1  and will be ongoing
  • Ground floor Kitchen delivered to site next week, installation will be on going
  • Internal paint –ground final coat will be on going , 1st on level 2 complete by end of week
  • Internal light court waterproofing and pavers, completed.
  • External waterproof membranes to panels is complete.
  • External framing for cladding for balconies completed.
  • External claddings (linings) in progress
  • External paint – started, ongoing scope
  • External shrouds and screening commenced and will be ongoing.
  • Level 2 pre-cast panels installation , this week
  • Formwork for Level 3 Suspended slab, starting next week
  • Electrical works and reinforcement for last part of ramp complete by end of this week
  • Pouring ramp on 17Th May
  • Civil works on ramp area , starting on 28th June
  • Lifts delivery on  17th July

 

The builder has advised they anticipate construction completion will be around late November.

Kind Regards,
Customer Care | Eton Property Group