Neue, Highett | June 2023

Dear Neue Purchasers,

Please find the following updates below from the builders on-site:

  • Internal services (HVAC) Basement rough-ins are completed
  • Internal services (Fire – wet) rough in Level 3 and corridors due to be completed by the end this month.
  • Internal services (Electrical) Mains completed, starting cut outs in ground level apartments – will be ongoing scope
  • Roofing works to lower roofs structure, completed this month( south )
  • Internal plaster sheeting has been started on L1 late next week with L2 & L3 to follow progressively
  • Plaster stopping have started on level 1  and will be ongoing
  • Ground floor Kitchen delivered to site installation will be on going
  • Internal paint – 1st coat will be on going with finish ceilings follow progressively
  • External waterproof membranes to balcony hobs waiting to be rectified
  • Internal waterproofing and shower screeds completed on ground level
  • External framing for cladding for balconies in progress ,due to be completed this month.
  • External claddings (linings) in progress
  • Internal light court waterproofing and pavers  Due for completion before month end.
  • External shrouds and screening commenced and will be ongoing.
  • Level 1 pre-cast panels installation , completed
  • Ground works and reinforcement for ramp walls, completed
  • Pouring ramp walls on 17Th May
  • Civil works on ramp area , starting on 22nd May

The builder has advised they anticipate construction completion will be around late November.

Kind Regards,
Customer Care | Eton Property Group