Neue, Highett | Q1 2023
Dear Neue Purchasers,
Please find the following updates below from the builders on-site:
- Services rough-ins to apartments Grd to L2 (hydraulics, fire, mechanical) is 90% completed
- Services rough-in to apartments Grd to L2 (electrical) commences 16/01
- Services rough-ins to B1 & B2 70% completed
- Works to B1 exit ramp commenced
- Crane slab infils all completed with formworks due to be dismantled end of next week
- L3 framing and roof framing to be completed by 13/01
- Roofing installation scheduled to commence prior end of January
- External cladding commenced late December
- Glazing (windows and sliders) Grd to L3 95% completed
- Set outs, earthworks and screw piles to townhouses completed
- In-ground services to townhouses commences 16/01
The builder has advised they anticipate June or July for construction completion.