Neue, Highett | Q4 2022

Dear Neue Purchasers,

Please find the following updates below from the builders on-site:

  • Framing completed G/flr to L2
  • Windows frames only, G/flr to L2 98% complete
  • Mechanical ceiling rough in G/flr complete, L1 70%
  • Fire rough in G/flr & L1 complete
  • Plumbing ceiling rough-in 95% complete G/flr to L2
  • Retaining walls 60% complete

This month’s targets:

  • L3 wall framing, trusses to follow on in November
  • Wall rough-ins for all service trades
  • Scaffolds start to perimeter
  • Cladding start late this month
  • More retaining walls
  • Tower crane removal 7th November