Neue, Highett | Q4 2022
Dear Neue Purchasers,
Please find the following updates below from the builders on-site:
- Framing completed G/flr to L2
- Windows frames only, G/flr to L2 98% complete
- Mechanical ceiling rough in G/flr complete, L1 70%
- Fire rough in G/flr & L1 complete
- Plumbing ceiling rough-in 95% complete G/flr to L2
- Retaining walls 60% complete
This month’s targets:
- L3 wall framing, trusses to follow on in November
- Wall rough-ins for all service trades
- Scaffolds start to perimeter
- Cladding start late this month
- More retaining walls
- Tower crane removal 7th November
Kind Regards,
Customer Care | Eton Property Group