Project Update – August 2020

JD Group & Hickory Group are pleased to advise that construction at Victoriana is progressing well with the following works being completed.

  • Roof plant screen
  • Bin chute installation complete
  • High level services installation rough-ins: hydraulics at Level 15, mechanical & electrical at Level 14
  • Concrete poured for Apartments 10.07, 14.01 and 14.05 pool
  • Plaster sheeting Level 10 apartments
  • Level 4 at final fit-off stage
  • Joinery, tiling and timber flooring install up to Level 7
  • Ground Floor metal screens & gates
  • Ground Floor canopy glazing.

With Victoriana progressing well, anticipated completion is expected in mid-2021.